When calling in an inspection, please make sure to leave all of the following information:
NOTE: Inspections must be called into the office before 3 PM for service on the next business day.
Footing: While installing stone bed and foundation drains.
Foundation: After sill plate is set and prior to back filling.
Footing: Prior to pouring concrete and with applicable reinforcement installed. REINFORCEMENT NOTE: All reinforcement must be installed on chairs or approved equal and appropriately lapped and tied including corners.
Foundation: Prior to backfilling, after damp-proofing, foundation drains and insulation is installed.
Underground Plumbing: Prior to covering, drainage, and/or waterline with appropriate test.
Plumbing Rough-In: All drain waste and vent lines complete with appropriate test.
Plumbing Final: All equipment and fixtures set and functional.
Electrical Rough-In: Prior to insulation, all wiring and boxes shall be installed. All grounds shall be made for this inspection.
Electrical Final: All equipment and fixtures set and functional.
Mechanical Rough-In: Prior to covering, gas piping test is required and all duct work joints must be taped.
Mechanical Final: All equipment and fixtures set and functional.
Framing: Prior to insulation or covering, after all rough in inspections are passed. Prior to roof or wall sheathing. Note: This inspection may be done in phases
Insulation: Insulation installed and all penetrations in top/bottom plates sealed.
Wallboard: Wallboard started and before any wall finishing.
Final: All steps, railings, decks, and interior and exterior finishes complete prior to occupancy.
2879 Mercer Butler Pike, Grove City, PA, USA
Office Phone: 724-406-0031 Fax: 724-406-0119 Email: risbuildingpermits@gmail.com Property Maintenance Email: richardson.compliance@gmail.com
Open today | 09:00 am – 03:00 pm |
Copyright © 2024 Richardson Inspection Services - All Rights Reserved.
Inspections are performed Monday - Thursday, Friday is an admin day.